How to file a mechanics lien in North Carolina
Unpaid for work or materials on a North Carolina construction project? Real-property liens and liens on funds are different remedies. Use this guide to organize the filing questions, then check the cited law against your role and project.
NC · PRIVATE CONSTRUCTION CLAIMS
Real-property liens and liens on funds are different remedies.
Section 44A-12 requires a claim of lien on real property no later than 120 days after last furnishing at the improvement site.
Notices to check before filing
Section 44A-11 requires service on the record owner and, for specified subrogation claims, the contractor. Identify whether your position also involves a lien upon funds or lien-agent notice.
Where and how to file in North Carolina
File the claim with the clerk of Superior Court in each county containing the property.
A filing mistake to avoid
A subcontractor cannot assume every rule for a direct owner-contractor claim applies unchanged.
Prepare your project records
Map the contract chain and gather first and last furnishing dates, property information, notice history, and the amount after credits.
- Identify who hired you and whether the property is privately owned.
- Confirm your notice obligations and the event that starts each time limit.
- Verify the owner and property description using appropriate records.
- Reconcile invoices, payments, credits, and disputed amounts.
- Keep filing and service receipts, and calendar any enforcement deadline.
After the claim is filed
Filing does not guarantee payment or establish that a disputed claim is valid. Preserve the filed document and delivery evidence. If payment arrives, arrange the required release or satisfaction. If the balance remains unpaid, seek advice about enforcement before its separate deadline expires.
Help with your unpaid construction account
The Credit App offers administrative mechanics lien preparation and a recording attempt for $249. Confirm your state, project, notices, and timing before ordering. The service uses the information you provide; it does not determine legal sufficiency, verify ownership, or represent you in an enforcement action.
Review the lien service · Compare service fees · Ask support about your project
Sources for North Carolina lien requirements
North Carolina General Statutes, Chapter 44A, Article 2
Sources checked September 23, 2026. This is a general guide to private construction claims, not a calculation of your deadline or legal advice. The cited edition and later amendments must be checked for your project.
Related guides